Site Planning Services
|
|
- The customer contacts the DSD Site Planning
counter in person or by phone and is provided a Pre-Application
Meeting1 checklist that outlines the steps to schedule a pre-application
meeting with DSD’s development review team. After preparing necessary documents, customer returns to the central log-in counter with plans and the required Site Development Civil Engineering Services Submittal Form1. If the submittal is incomplete, the customer is directed to make corrections and return after deficiencies are addressed. If the submittal is acceptable, review fees are collected
|
 |
- The pre-application meeting is held with the project team leader,
City staff, and the customer to
review the project, time lines, plans, identify development challenges
and opportunities, and outline
Code issues. The customer is provided a project-specific information
packet detailing the preliminary site plan submittal, and advised
that a project may proceed to the next step only when plan elements
are complete and all issues have been resolved.
|
 |
- The customer submits their preliminary
site plan package1 and associated documents to Central
Log-in, where plans are routed to departments, agencies, and
utility companies for review and comments. Incomplete submittals
will not be processed. DSD staff will develop a report and mark
up the preliminary plans, documenting the conditions for final
site plan approval. The applicant will be contacted by DSD for
the preliminary review meeting, which may be optional or required,
depending on the scope of the project and comments received during
staff review.
|
 |
- DSD staff, invited neighbors, and the customer meet to discuss
the submittal, review the staff report outlining conditions of approval,
and mark up the site plan and associated documents. Staff will present
details that will assist the customer to develop the final construction
documents (i.e. site plan, grading and drainage, life/safety, water,
sewer, paving, concrete, and building elevations).
|
 |
- If the preliminary site plan review is granted, the customer may submit
construction plans for
review and approval to Central Log-in as
required. The customer is responsible for satisfying all
conditions of approval prior to obtaining the necessary permits.
(Note: The building plan submittal will require pre-approval by the
team site planner prior to submitting the plans to Central Log-in.
If necessary, please contact your team leader.)
|
 |
- A variety of permits may be required for your project, based on
the preliminary site plan report. Each major plan review has a separate
process, and must be coordinated, in sequence, prior to obtaining
the building permit. If you have questions regarding the sequencing
of construction plans, please contact your project team leader.
|
1requires Adobe Reader to view